Summer Special Flat 65% Limited Time Discount offer - Ends in 0d 00h 00m 00s - Coupon code: suredis

PMI PMI-RMP PMI Risk Management Professional (PMI-RMP) Exam Exam Practice Test

Demo: 79 questions
Total 264 questions

PMI Risk Management Professional (PMI-RMP) Exam Questions and Answers

Question 1

A product roadmap should contain which of these primary components?

Options:

A.

Detailed design plan, business objectives, timeframes

B.

Project management plan, communications management plan, stakeholder engagement plan

C.

Project release timeframes, detailed design plan

D.

Product vision, business objectives, timeframes

Question 2

The trigger for a highly categorized threat has occurred. The risk has a set response plan.

Who is responsible for developing responses to risk and monitoring the implementation status of the risk response?

Options:

A.

Product Manager

B.

Risk Action Owner

C.

Risk Owner

D.

Project Manager

Question 3

A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment

What should the risk manager do?

Options:

A.

Confirm the risk triggers are still valid.

B.

Ask the architect to develop acceptance criteria.

C.

Review the feature with the project team.

D.

Escalate the issue to the project board.

Question 4

During the design phase the project team is exploring various architecture options. After reviewing the results of design pilot, two conflicting infrastructure pieces were identified.

What action should the project manager take?

Options:

A.

Reassess the design for the two pieces.

B.

Escalate the situation and request approval to move forward.

C.

Confirm the results through a second pilot.

D.

Update the assumptions log and assess the risk associated with it.

Question 5

A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.

What should the risk manager do next with the data set?

Options:

A.

Perform a probability and impact assessment

B.

Perform Monte Carlo simul-ations

C.

Perform a sensitivity analysis

D.

Perform a risk data quality assessment

Question 6

As per the risk analysis process carried out for a project, two risks are registered. The probability risk A will occur is 40% and its monetary impact to the project is US$100,000. The probability risk B will occur is 60% and its monetary impact to the project is US$20,000.

What is the total contingency budget that should be created?

Options:

A.

US$68,000

B.

US$52,000

C.

US$120,000

D.

US$80,000

Question 7

While performing risk identification exercises, the risk manager often encounters biases from the project team. How can the risk manager accurately identify what will trigger a risk?

Options:

A.

Remind the project team to keep an open mind

B.

Review the results with the project manager afterward

C.

Review published operational experience reports

D.

Use the mean answers provided by the project team 

Question 8

A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.

What should the risk manager do?

Options:

A.

Ask the project sponsor if every risk in the risk register can have the same priority.

B.

Mark every identified risk as an extremely high priority and any future risks as a lower priority.

C.

Agree with the SME, treat every risk with equal priority, and inform all stakeholders.

D.

Perform a sensitivity analysis and determine the correct priority of every identified risk.

Question 9

A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.

What should the project manager do?

Options:

A.

Avoid the risk

B.

Transfer the risk

C.

Ignore the risk

D.

Accept the risk

Question 10

A risk manager for a financial organization is assigned to support a project team in developing a custom software solution to manage loans. Which document should the risk manager request first from the project sponsor to identify major risks?

Options:

A.

Risk management plan

B.

Clients' credit scores

C.

Organization's mission and vision

D.

Historical data from the credit portfolio

Question 11

The project manager asks the risk manager to determine the initial risk assessment for a six month initiative that is about to kick-off. Which two artifacts will help the risk manager conduct the related analysis? (Choose two.)

Options:

A.

Work breakdown structure (W&S)

B.

Project organizational chart

C.

Configuration management plan

D.

Brainstorming

E.

Monte Carlo analysis

Question 12

The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?

Options:

A.

Use the Delphi technique involving experts who have identified opportunities in the past

B.

Interview more stakeholders who have a positive mindset

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Conduct a political, economic, sociological, technological, legal, and environmental (PESTLE) analysis

Question 13

A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.

What should the risk manager do in this scenario?

Options:

A.

Review project schedule estimates.

B.

Change the response strategies.

C.

Reduce the contingency reserves.

D.

Conduct a risk planning workshop.

Question 14

Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.

How should the risk manager proceed?

Options:

A.

Perform a qualitative risk analysis and update the results.

B.

Update the assumptions/exclusions register with the new information.

C.

Update the risk register and prepare for the Monte Carlo analysis.

D.

Perform a quantitative risk analysis and update the results.

Question 15

A risk manager administered a pre-workshop risk survey in preparation for the upcoming workshop. The workshop invitees participated in the survey and submitted many risks encompassing all project phases and risk areas. The risk manager sorts risks by similarities and categories for the workshop.

What should the risk manager do next to visually organize the risks?

Options:

A.

Develop an affinity diagram

B.

Perform the analytical hierarchy process

C.

Perform a SWOT analysis

D.

Assign probability and impact

Question 16

A core project team is working on unrelated tasks in advance to reduce the risk of delay due to an external team not completing its tasks on time. The core project team has completed all possible unrelated tasks but cannot move forward, because the external team's tasks have yet to be completed.

What should the risk manager do next?

Options:

A.

Start a quantitative analysis to understand the impact.

B.

Crash the schedule to mitigate the risk consequences.

C.

Transfer the risk to the external team.

D.

Ask the risk owners to review the risk response plan.

Question 17

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Options:

A.

Add contingencies to other tasks to mitigate similar risks.

B.

Reassess risks with a new assumptions and constraints analysis.

C.

Review the risk response plan looking for lessons learned.

D.

Log the event in the issue log and update the project management plan.

Question 18

A risk manager for a hospital extension project is leading a project team in developing a risk management plan. One team member is responsible for conducting risk identification. The team member just joined the team and is struggling to ensure the coverage of all risks that might arise in this complex project.

How should the risk manager address this concern?

Options:

A.

Develop a risk breakdown structure {RBS) to identify possible risks.

B.

Develop a risk impact analysis to assess the consequences of possible risks

C.

Develop a probability and impact matrix to analyze possible risks.

D.

Create a risk register to capture and track possible risks. 

Question 19

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Options:

A.

Reformed the risk monitoring and closing process properly.

B.

Created the project work plan and budget more accurately.

C.

Educated the project team on budget change requests.

D.

Communicated better with the organization's CEO.

Question 20

During a project's initial planning session, the project team identifies a possible risk. The team is under the impression that a critical vendor might delay delivery. This could impact both the project schedule and budget. The team shares insights on the risk's likelihood and impact with the risk manager.

What should the risk manager do?

Options:

A.

Assume the vendor will deliver on time and focus only on internal risks.

B.

Allocate contingency funds without first evaluating the risk's probability and impact.

C.

Wait indefinitely for the vendor's update before analyzing the risk.

D.

Assess the risk using a probability-impact matrix and prioritize it based on its score.

Question 21

A project has suffered a big schedule delay and there are still some risks that are close to materializing. The project manager is concerned about communicating this risk level, because the stakeholders might suspend project funding and cancel the project.

How should the risk manager manage the risk level?

Options:

A.

Communicate risk levels only to the supportive stakeholders.

B.

Advise the sponsor to meet with the stakeholders to discuss the risk levels.

C.

Collaborate with the project manager to communicate risk levels to stakeholders.

D.

Coach the project manager on communicating risk levels to stakeholders.

Question 22

A risk manager is facilitating a risk identification workshop on a new product with technical experts. There is no consensus among the technical experts on most of the identified risks and their characteristics. The risk manager decides to resolve this difference using another technique.

Which technique should the risk manager use in this situation?

Options:

A.

Brainstorming

B.

Delphi method

C.

Focus group

D.

Checklist analysis

Question 23

While developing a risk management plan for a complex program in a metricized environment, a program management team is itemizing a response plan for each identified risk that appears in the risk register. What should the risk manager do to effectively monitor the risks?

Options:

A.

Present the complicated nature of the program risk responses to the sponsor for proper advice.

B.

Determine the workarounds for the program risks and allocate responsibilities to the team.

C.

Allow the most experienced program manager to handle the most critical program risks.

D.

Encourage the program team to assume risk ownership prior to delegation. 

Question 24

A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.

What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)

Options:

A.

Scope of work and requirements

B.

Monte Carlo analysis from a similar project

C.

List of pre-approved contractors

D.

Organization chart for city permit department

E.

Risk management plan

Question 25

A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.

What should the risk manager do first?

Options:

A.

Perform an assumptions and constraints analysis.

B.

Use the Wideband Delphi method.

C.

Use the brainstorming technique.

D.

Perform a strength, weaknesses, opportunities, and threats (SWOT) analysis. 

Question 26

A project team in a multinational organization is working on a risk management plan for a multimillion-dollar project. This project involves three global regions with a wide range of critical stakeholders with varying degrees of risk appetite.

What should the risk manager advise the project team to do?

Options:

A.

Align the project risk thresholds with the risk appetite of a critical region.

B.

Align the project risk thresholds with the organizational risk appetite.

C.

Concentrate on the risk appetites of the influential stakeholders.

D.

Concentrate on the risk appetites of the vulnerable stakeholders. 

Question 27

A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.

What type of request is the risk manager describing?

Options:

A.

A request to increase project earnings

B.

A request to increase project resources

C.

A challenge to stakeholder thresholds

D.

A challenge to the project investment 

Question 28

Which statement describes the risk portrayed on the risk matrix heat map below?

Options:

A.

The risk has a probability of 60% of occurrence and a medium impact rating.

B.

The risk has a probability of 40% of occurrence and a high impact rating.

C.

The risk has a high impact and probability of occurring.

D.

The risk has a low probability and high impact rating.

Question 29

A project team is presenting a delivery plan to a client. Some of the client's experts do not feel comfortable with some activities at a critical stage. The experts ask to change the plan and present a better alternative.

What should the risk manager do first?

Options:

A.

Review and update the project quality management plan.

B.

Conduct a risk assessment process for the critical stage.

C.

Create a more detailed work breakdown structure (WBS).

D.

Add additional time to the delivery plan to cover issues.  

Question 30

A risk manager has a well-structured risk management process in place for a complex project with a tight schedule. Despite implementing preventive actions, one of the risks identified in the early stages of the project has still occurred and is now an issue.

What should the risk manager do next?

Options:

A.

Meet with the project team to brainstorm potential solutions to the problem.

B.

Implement the risk response plan to remedy the problem as soon as possible.

C.

Initiate discussions with the project manager to decide how to manage the problem.

D.

Escalate the problem to the project sponsor to agree on the best course of action. 

Question 31

A risk manager for a large project has completed documenting the risk management plan. The project is moving from planning to execution.

Which three actions should the risk manager take to ensure the risk management plan remains effective during the project timeframe? (Choose 3)

Options:

A.

Verify whether or not any identified risks might occur and implement the risk response plan.

B.

Regularly check and report on the status of risks identified according to their prioritization.

C.

Monitor the status and oversee execution of the risk response plan for each identified risk.

D.

Ensure management reserves are sufficient to cover the mitigation plans for all identified risks.

E.

Allocate and lock in project resources according to the initial risk prioritization for all identified risks.

Question 32

Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?

Options:

A.

When the forecast activity date has been met or exceeded

B.

When the stakeholders agree a risk is no longer applicable

C.

When the risk has been realized and can no longer happen again

D.

When iterative data analysis determines the risk is not applicable

Question 33

A risk manager is confident that they have identified and quantified the risks and opportunities for a project. When presenting their work to management, on what areas should the risk manager focus? (Choose two.)

Options:

A.

Risks that are tied to the success of the organization

B.

Risks as they apply to the organization's overall risk management philosophy and strategic ambition

C.

Huge opportunities that possibly bring an additional 30% return for 10 projects in the next year

D.

Risks related to cost that will impact the major projects that are currently in the execution phase

E.

Risk mitigation actions that will require work from stakeholders

Question 34

During project execution, a project manager invites the stakeholders to a risk review meeting. During this meeting, a vendor highlights that the mitigation plan for a schedule risk has generated an additional risk.

What should the risk manager do first?

Options:

A.

Update the new risk in the risk register.

B.

Plan responses for the new risk.

C.

Passively accept the new risk.

D.

Add the new risk to the watch list.

Question 35

An undocumented risk is realized during the rollout of a new product line important to the company. The product owner escalates this matter to the company president, who expects all risks to be documented in the project risk plan.

How should the risk manager address this concern?

Options:

A.

Risks are documented to the practicable extent possible.

B.

Probability of the risk was very low. so the risk was not documented.

C.

Impact of the risk was assessed to be insignificant, so the risk was not documented.

D.

A similar risk never occurred in the past, so it was not considered. 

Question 36

During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?

Options:

A.

Strengths, weakness, opportunities, and threats (SWOT) analysis

B.

Delphi technique

C.

Decision tree analysis

D.

Probability impact matrix

Question 37

An organization with a portfolio of unique business functions kicks-off a performance improvement project across the entire organization. There are a large number of stakeholders the project team will need to consider during risk identification.

What three actions should the risk manager ensure the project team performs during risk identification? (Choose 3)

Options:

A.

Develop checklists based on historical information

B.

Conduct interviews, meetings, and focus groups

C.

Assign a different risk manager for each portfolio unit

D.

Employ brainstorming to generate spontaneous ideas

E.

Perform qualitative and quantitative risk analyses 

Question 38

A risk manager has been assigned to a project in a company that is undergoing a significant cultural and organizational change. The risk manager will start planning risk management. activities with stakeholders but is unsure with whom to engage.

What should the risk manager do?

Options:

A.

Assign a subset of stakeholders to work on the risk management process.

B.

Leverage the project manager's project stakeholder analysis.

C.

Agree with the project manager not to start risk activities.

D.

Send a communication inviting volunteers to join risk activities.

Question 39

The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.

What should the project manager do?

Options:

A.

Wait until the weather improves before sending the equipment.

B.

Ask the project sponsor to approve shipping the equipment.

C.

Proceed with the planned risk response to move the equipment.

D.

Request the shipment of the equipment to satisfy the client.

Question 40

During project planning, a risk is identified for which the risk manager has defined a mitigation strategy. Later during project execution, this risk still leaves substantial residual risk.

What should the risk manager do to handle this situation?

Options:

A.

Revisit this risk in the risk register and redefine the mitigation strategy.

B.

Activate the contingency plan to handle this risk during execution.

C.

Mark this new risk as an extremely high priority and inform all stakeholders.

D.

Ask the project sponsor for more budget to deal with this risk.

Question 41

During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.

How should the risk manager address this concern?

Options:

A.

Compare the actual data with the historical data.

B.

Compare the actual data with the subject matter expert (SME) criteria.

C.

Compare the actual data with the risk baseline.

D.

Compare the actual data with the project sponsor's expectation.

Question 42

A risk manager is collaborating with project stakeholders and the project team to identify risks in a construction project. The risk manager intends to use an approach that engages stakeholders based on information, such as scope baseline and project estimates, while also determining risk impacts based on this approach.

Which risk identification approach should the risk manager use to achieve this goal?

Options:

A.

Strengths, weaknesses, opportunities, and threats (SWOT) analysis

B.

Brainstorming technique

C.

Delphi technique

D.

Assumptions and constraints analysis

Question 43

The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.

What should the project risk manager do next to identify risks?

Options:

A.

Review the risk breakdown structure to ensure project scope is covered.

B.

Use the brainstorming technique to remove personal bias.

C.

Use expert judgment to remove ego or emotional conflict.

D.

Consider the Delphi technique to gather all stakeholder opinions.

Question 44

During a project's planning phase, the project team identifies a potential supplier delay and marks it as a significant risk. A risk manager is tasked with effectively monitoring this risk.

What should the risk manager document as the risk trigger?

Options:

A.

The probability and impact rating of the supplier's delay on the project

B.

The response strategy, such as increasing inventory or finding an alternative supplier

C.

The specific event or condition, such as the supplier missing a delivery deadline

D.

The threshold for acceptable delay, such as a maximum of three days before impacting project milestones

Question 45

A project manager for a predictive project just received a scope change request where additional development is required. What should the risk manager do to support the project manager with this scope change request?

Options:

A.

Evaluate any new risks that are introduced due to the change in scope.

B.

Update the risk management plan to reflect the scope change.

C.

Reassess the identified risks that impact the project scope.

D.

Update the risk register to identify, analyze, and plan a response for any new risk.

Question 46

A new vice president in one of its divisions observed that the portfolio of projects within their division experienced significant variations beyond the ±10% established threshold with the potential of not achieving its overall business goals. Hence, they directed all project leaders and sponsors to ensure that they set and work toward more stringent thresholds of ±5% and reports on the basis of any variance outside that range.

How should the risk manager respond?

Options:

A.

Assess the impacts of this change but do nothing as the project is still within the enterprise-wide threshold.

B.

Assess and modify the project risk management plan in response to the new directive.

C.

Accept project risks since it is already within the enterprise-wide threshold.

D.

Advise that the decision could increase the risk of their portfolio exponentially.

Question 47

An agile project manager has noticed their team's declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Introduce performance standards and evaluation methods.

B.

Clarify project goals and project contract constraints.

C.

Promote cross-training and mentoring among team members.

D.

Develop a reward system related to position and years of experience.

Question 48

A risk manager documents the causes in the risk register and needs to ensure the risk is adequately described. What is critical for the risk manager to consider when describing the causes?

Options:

A.

Each cause has a degree of uncertainty

B.

Each cause has well defined owner

C.

The causes represent actual conditions

D.

The causes must be validated by the risk owner

Question 49

A risk manager is integrated into a team overseeing a crucial software development project. During the information gathering phase, the risk manager notices significant weaknesses in the maturity of the risk management process. The team needs to establish a more structured approach to managing risks, including the documentation of strategies, ownership structures, and details about the organization's project risk baseline.

What should the risk manager do?

Options:

A.

Prioritize the risk management plan.

B.

Arrange the risk mitigation plan.

C.

Create a risk action plan with risk owners.

D.

Prioritize the risk register.

Question 50

A project is in progress when the product team requests a change to the scope. The team indicates that this is a minimal change and should not create any problems.

What should the risk manager do next?

Options:

A.

Update the work breakdown structure (WBS).

B.

Analyze any potential impact.

C.

Escalate the issue to management.

D.

Add a new risk to the risk register.

Question 51

The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.

How should the project manager and the risk manager handle this situation?

Options:

A.

Ensure the project complies with the current traffic regulations and laws.

B.

Send a letter to the traffic authority with the general project information.

C.

Perform inquiries on the website of the traffic authority weekly.

D.

Meet with the traffic authority staff in charge of the new regulation.

Question 52

Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simu-lation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.

Which tool should the risk manager consider for assessing the test risk?

Options:

A.

Scenario analysis

B.

Sensitivity analysis

C.

Probability and impact matrix

D.

Monte Carlo simul-ation 

Question 53

A risk manager is reviewing documentation for a project following a risk planning workshop with project stakeholders and team members. Several items have been identified on the risk log that would be detrimental to project success, but the associated triggers cannot be managed by the organization and are unlikely to occur.

Which response should the risk manager recommend for these risk items?

Options:

A.

Mitigate

B.

Accept

C.

Enhance

D.

Exploit

Question 54

A critical piece of equipment broke during a project execution phase. The risk manager notices this risk in the risk register, and the response is to rent equipment until the critical piece is repaired.

What type of risk response is this?

Options:

A.

Transfer

B.

Accept

C.

Mitigate

D.

Avoid 

Question 55

What is an example of legal and regulatory requirements and/or constraints when assessing a project environment for threats and opportunities?

Options:

A.

Organizational communication requirements

B.

Organizational standard policies, processes, and procedures

C.

Formal knowledge sharing and information sharing procedures

D.

Confidentiality of project information

Question 56

The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.

What should the project manager do regarding those risks?

Options:

A.

Review the assumptions analysts

B.

Conduct a checklist analysis on each risk

C.

Create a risk response plan for those risks

D.

Review the risk register to check for the new risks

Question 57

A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.

What should the project manager have done differently?

Options:

A.

Executed the Monte Carlo sensitivity analysis prior to mobilization

B.

Added generic construction risks to the risk register before construction began

C.

Reviewed the assumptions/exclusions register in the project charter

D.

Performed risk identification exercises for the full lifecycle of the project

Question 58

Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?

Options:

A.

Exclude risk averse stakeholders from future risk discussions

B.

Explain risk handling and mitigation strategies

C.

Increase the impact of all risks in the risk breakdown structure (RBS)

D.

Develop a generous probabilistic cash flow model

Question 59

An organization with a large computer network identified a potential cyber security threat. Although certain measures were implemented to avoid the risk, the cyber security threat occurs. The measures were partially successful and a new unforeseen risk emerges.

What should the risk owner do?

Options:

A.

Develop an efficient network protection solution quickly to mitigate the risk.

B.

Escalate the case to the risk manager and wait for their instructions.

C.

Conduct an analysis to determine the root cause of the failed response.

D.

Apply a work around to eliminate or mitigate the impact of the threat.

Question 60

The project risk manager for an environmental preservation project has started the process of monitoring and controlling risks, The project manager has asked the project team to document the results of this process.

How should this documentation be utilized in the future?

Options:

A.

To return the remaining amount of the contingency reserve

B.

To ensure information is recorded for lessons learned

C.

To comply with the rules and regulations

D.

To hold those who created the risk accountable

Question 61

Several key stakeholders approach the project manager with concerns. The stakeholders have received feedback from local businesses that have reported a reduction in customers because of construction activities at the worksite, and they plan to submit a claim to the municipality to fine the project manager's company.

How should the project manager address this concern?

Options:

A.

Evaluate the risk with the team and update the issueing

B.

Discuss the concern with the local business owners.

C.

Update the key risks and perform a quantitative risk analysis.

D.

Adjust construction work hours to after business hours.

Question 62

A web page for weather reports will be online next quarter. During the retrospective, discrepancies were discovered with the customer’s requests and the user experience (UX). There is a disagreement between the product owner and the development team about what may have gone wrong and led to this.

What should the Extreme Programming (XP) coach do to keep the project on track and deliver on time?

Options:

A.

Release this version and leave changes to be done at the end of the project phase.

B.

Arrange a workshop where all ideas will be discussed and take corrective actions ensuring value delivery.

C.

Ask the development team to brainstorm and come up with suggestions that will improve the delivery date.

D.

Run a spike, identify what went wrong during implementation, and request a change to enhance value delivery.

Question 63

The risk manager of a major project needs to ensure the organizational process assets (OPAsj are updated as a result of risk management activities. How will the risk manager accomplish this?

Options:

A.

Ensuring that the project sponsor is kept well-informed

B.

Arranging periodic risk: management process audits

C.

Communicating the status of risks regularly to stakeholders

D.

Monitoring costs with intervention when necessary

Question 64

After the initial assessment of a new project, a project manager found that in order to complete the expected results, detailed and exhaustive planning will be required to ensure the product's characteristics and quality. What should the risk manager propose to the project manager what to do?

Options:

A.

Use a predictive approach for the delivery.

B.

Use a hybrid approach for the delivery.

C.

Use an adaptive approach for the delivery.

D.

Use an agile approach for the delivery. 

Question 65

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project’s success and do not believe that the benefits are significant.

What should the risk manager do?

Options:

A.

Schedule a meeting to review and develop realistic risk thresholds with the project team.

B.

Motivate and influence the project team with risk engagement activities like workshops.

C.

Ensure that risk management responsibilities are clearly identified in the risk management plan.

D.

Ensure that the risk language used by all stakeholders is consistent with the risk management plan.

Question 66

A risk manager is conducting a qualitative risk analysis for a renewable energy project that faces tight deadlines. The team identifies risks such as weather unpredictability, material cost fluctuations, and potential regulatory delays. While some members advocate prioritizing high-likelihood risks, others emphasize addressing unlikely but high-impact risks.

What should the risk manager do?

Options:

A.

Focus on high-probability concerns first to proactively address the most immediate threats.

B.

Delegate the assessment of lower-priority concerns to team leads while addressing critical ones.

C.

Evaluate all identified concerns and consider likelihood and impact to prioritize the concerns effectively.

D.

Prioritize uncertainties that align closely with the project's primary deliverables.

Question 67

A risk manager has been assigned to an upcoming project. A senior risk manager within the organization recently completed a similar project and has provided a lessons learned document to aid planning efforts for the upcoming project. Upon reviewing the document, the risk manager discovers that the completed project was delivered several months behind schedule and several thousands of dollars over budget. The root cause was determined to be an unforeseen risk trigger that caused several items to be reworked, creating cascading schedule delays and depleting management reserves.

What should the risk manager do to mitigate the chance of the same issues reoccurring?

Options:

A.

Ensure that all project stakeholders have a copy of and understand the project's risk management plan.

B.

Increase the management reserves and inform stakeholders of what is available to cover any unexpected expenses

C.

Distribute the lessons learned document to stakeholders knowing that the likelihood of reoccurrence is low.

D.

Document the known risk triggers as the identified cost and schedule risks in the risk register. 

Question 68

A list of risks was identified that could occur during the design phase. Now, the team finished the design phase and those risks did not materialize.

What should the project manager do next?

Options:

A.

Close the risks and update their status in the risk register.

B.

Use their contingency with other risks that are still open.

C.

Remove the risk from the list as they are no longer applicable.

D.

Reevaluate those risks' severity, and update the risk register.

Question 69

When approving the risk contingency budget for a project, the CEO notices each team has a different approach to report risks and their impacts. The CEO decides to create a new centralized risk management function to help resolve the problem.

How does centralizing the risk management function help resolve the problem?

Options:

A.

Enhance the process of identification of different Individual project risks.

B.

Allows monitoring the impact against the overall project risk exposure.

C.

Establishes risk sources and ownership for trigger monitoring.

D.

Creates a single repository for all project risk documents.

Question 70

A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.

How should the project manager handle stakeholder expectations?

Options:

A.

Add buffers to the schedule to accommodate risk.

B.

Ensure the risk register includes all identified risks.

C.

Discuss the risk response strategies with the stakeholders.

D.

Develop a communication plan to share updates on risks.

Question 71

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?

Options:

A.

Add more float to the key activity

B.

Add more contingency to the project

C.

Review the plans for the key activity

D.

Increase the budget for the key activity

Question 72

A project is In the initiation phase. The project stakeholders are Invited to a meeting to share their thoughts that may impact the project In a positive or negative way.

What will be the main output of this meeting?

Options:

A.

Evaluating the project's probability of success

B.

Identifying threats and opportunities

C.

Evaluating the project's impact

D.

Performing a qualitative analysis

Question 73

The sponsor of a construction project is upset about the results of the risk management team. The sponsor believes the team did not properly identify the risks that could affect the project. The team did manage the risks; however, some of the risk response strategies created secondary risks.

What should the risk management team have done to manage this situation?

Options:

A.

Ensured to include the stakeholders in the team discussions

B.

Encouraged involvement of the project team during the review meetings

C.

Enhanced communication with the sponsor regarding secondary risk impact

D.

Ensured the sponsor got more involved with the project risk planning

Question 74

A newly assigned risk manager realizes that a project has unrealistic funding and low resources. Which document should the risk manager review?

Options:

A.

Risk assessment criteria

B.

Project management plan

C.

Project assumptions

D.

Risk management plan 

Question 75

A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.

What should the risk management professional do next?

Options:

A.

Perform a sensitivity analysis to the higher-level aggregate activities

B.

Develop a risk breakdown structure (RBS) identifying the potential risk categories

C.

Conduct a strengths, weaknesses, opportunities, and threats (SWOT) analysis

D.

Perform a base line Monte Carlo simul-ation to address overall threats to project objectives

Question 76

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

Options:

A.

Prompt lists

B.

Interviews

C.

Delphi technique

D.

Nominal group technique

Question 77

When selecting strategies as an activity of Plan Risk Response, what is the overall goal?

Options:

A.

Select the strategies with the least overall impact to resources.

B.

Select the strategies with the least financial impact.

C.

Select the strategies with the greatest overall positive influence.

D.

Select the strategies with the greatest benefit to stakeholders.

Question 78

A financial service firm adheres to heavily regulated compliance legislation. During the firm's latest project, the Chief Financial Officer (CFO) and the Chief Information Officer (CIO) endorsed a risk-based approach. This approach ensured compliance with the legislative requirements for properly storing confidential employee salary information. The risk manager recorded this information in the project's risk management plan.

What is the organization's risk maturity level?

Options:

A.

No maturity

B.

Low maturity

C.

Medium maturity

D.

High maturity

Question 79

A project team has failed to complete an important project milestone on time. The team was counting on an external provider to deliver key equipment on a specific date but the provider was delayed.

What should the risk manager have done to prevent missing the milestone?

Options:

A.

Better schedule monitoring and controlling.

B.

Identify and analyze project plan assumptions.

C.

Have a detailed work breakdown structure (WBS).

D.

Use management reserves to cover delays.

Demo: 79 questions
Total 264 questions